RPL achieves 82% overall progress in just 24 months

16 Jan '08
4 min read

Reliance Petroleum Limited (“RPL”) has successfully completed the second year of implementation of its complex refinery, coming up in a Special Economic Zone at Jamnagar.

RPL has achieved 82% overall progress in just 24 months since commencement of the Project. Based on the progress so far, RPL is on course to complete the project ahead of its initial schedule of December 2008.

During the quarter, project implementation gained further momentum and led to achievement of several significant milestones:
• Engineering activities are nearing completion.
• Overall procurement progress exceeded 97%.
• More than 75% of equipments and tagged items already received at site.
• Deliveries of over dimensional cargos (ODC) and super ODCs are nearing completion.
• Over 40% of equipments have been erected; Project skyline changed dramatically.
• Overall construction progress crossed the 60% mark for the complex.
• Structural and pipe fabrication activities progressing at an accelerated pace.
• Sufficient site infrastructure mobilised to sustain equipment installation and fabrication activities on the fast track.

During the quarter, the project engineering activities were completed with all drawings for concreting, structural steel, underground piping as well as electrical and instrumentation released for construction.

Residual engineering activities to support ongoing construction are continuing. Successful completion of this massive engineering effort in less than two years has set a new global record in the refining sector.

It also reflects the success of a team effort that involved over 7,500 engineers, working from several interconnected locations across the world.

The quarter witnessed near completion of procurement activities for the project as well. The procurement and contracting for equipments, tagged items and bulk materials is now complete.

Equipment deliveries have gained enhanced momentum with over 3,800 equipments, including several ODCs and super heavy equipments, delivered at site already.

Nearly all the bulk materials, including pipes and fittings as well as substantial part of electrical and instrumentation bulks have also been received at site.

Leave your Comments

Esteemed Clients

TÜYAP IHTISAS FUARLARI A.S.
Tradewind International Servicing
Thermore (Far East) Ltd.
The LYCRA Company Singapore  Pte. Ltd
Thai Trade Center
Thai Acrylic Fibre Company Limited
TEXVALLEY MARKET LIMITED
TESTEX AG, Swiss Textile Testing Institute
Telangana State Industrial Infrastructure Corporation Limited (TSllC Ltd)
Taiwan Textile Federation (TTF)
SUZHOU TUE HI-TECH NONWOVEN MACHINERY CO.,LTD
Stahl Holdings B.V.,
Advanced Search