PEI undertakes maintenance shutdown of its ethylene cracker

30 Aug '08
1 min read

Panjin Ethylene Industry Corporation (PEI) pulled down the shutters of its 160 kt/per year ethylene cracking plant on August 11 for a maintenance turnaround which will last for a period of 25 days and will be brought back on stream by early September.

The outage came unannounced and was initiated four days before the scheduled plan because of some unprecedented problem faced at the facility and also due to bearish market trends.

Official spokesperson of PEI told Fibre2fashion that the plant is currently closed but is expected to restart very soon. However, the company is yet to decide the date for restarting.

A BTX plant of the corporation would also follow suit and undergo a maintenance turnaround which would last longer than that of the ethylene-cracker. The plant has a benzene capacity of 60 kt/year, toluene capacity of 16 kt/year and a xylene capacity of 9 kt/yr.

Other downstream plants of the corporation have also been closed for a turnaround in the afore mentioned period.

Fibre2fashion News Desk - India

Leave your Comments

Esteemed Clients

TÜYAP IHTISAS FUARLARI A.S.
Tradewind International Servicing
Thermore (Far East) Ltd.
The LYCRA Company Singapore  Pte. Ltd
Thai Trade Center
Thai Acrylic Fibre Company Limited
TEXVALLEY MARKET LIMITED
TESTEX AG, Swiss Textile Testing Institute
Telangana State Industrial Infrastructure Corporation Limited (TSllC Ltd)
Taiwan Textile Federation (TTF)
SUZHOU TUE HI-TECH NONWOVEN MACHINERY CO.,LTD
Stahl Holdings B.V.,
Advanced Search