Mitsubishi shelves operations of No 2 Ethylene Plant
06 Mar '08
2 min read
2. Schedule for restarting operations on cracking furnaces 2F-201-205 Around mid- to end-March
3. Production capacity after restarting operations Approximately 320,000 tons per year (Amounts to approximately 67% production capacity compared to that before the fire accident)
Taking this fire accident seriously, we will make a concerted effort to prevent a recurrence and restore confidence with thorough safety management in the Mitsubishi Chemical Group. We also continue to devote ourselves to secure products for our customers.